MoI Union Minister inspects air compressor test at Steel Mill (Pangpet)
28 JULY 2025
UNION Minister for Industry Dr
Charlie Than, accompanied by Shan State Chief Minister U Aung Aung, attended
the ceremony for the test run of Air Compressors installed at the air
purification plant of the No 2 Steel Mill (Pangpet) in Taunggyi Township of
Shan State on 26 July.
The Union minister pressed the
button of No 1 Air Compressor to run properly, inspected the operation system
of the air compressor, and No 2 Air Compressor.
inister said the permission was
achieved from the State Administration Council to implement the No 2 Steel Mill
(Pangpet) with three recommendations of TPE, and now recommendation 1 operating
air purification plant is initiated. The plant produces oxygen between 20,000
and 40,000 Nm³ (normal
cubic metre) and nitrogen between 400 and 1,200 Nm³ per hour, while it just needs 33,000 Nm³ oxygen and 21 run the Romelt
plant.
He continued that the materials
of the air purification plant were examined and installed by one expert from
TPE Co Ltd and nine experts from AGS Co Ltd starting from 12 May 2025, and the
main part of the plant Air Compressors were successfully operated.
Mr Senin of TPE Co Ltd, Mr Konev
of AGS Co Ltd and Mr Vladislav of Rostec briefed all on successful cooperation
and further work plans.
The Union minister presented
gifts and handed over a K5 million cash prize for the staff of the No 2 Steel
Mill (Pangpet) to the mill manager.
The No 2 Steel Mill (Pangpet)
project resumed on 4 October 2021, and 19 workshops in the mill are now
operating. The project will be finalized in November 2026. — MNA/KTZH

No comments